Turnaround Duration
3 days saved in total turnaround duration, significantly accelerating project delivery.


Chevron’s Gulf of Mexico team faced another high-stress turnaround window with over 300 components to inspect and repair. But this time, they used IntelliSpec’s offline-first Turnaround Execution Suite — cutting downtime by 3 full days, improving field coordination, and ensuring no critical asset was missed.
During past outages, the inspection and repair teams worked in silos. Paper forms delayed status updates. Field teams struggled with connectivity. By the time a flagged component was reported to planning, the part wasn’t ordered or available. They often lost 2–3 days just aligning on the facts.
“We were reactive. Everything felt urgent because nothing was transparent.” – Priya S., Turnaround Lead
Chevron GOM deployed IntelliSpec’s Turnaround Execution Suite, including:
Tablets were pre-loaded with inspection checklists and photo capture workflows. Even in offshore no-signal zones, teams logged findings that auto-synced once online.
Within 7 days of rollout:
Planning teams gained visibility. Priya could triage issues in the moment. Procurement could pre-order parts. And most importantly, no last-minute “gotchas” popped up during recommissioning.
“It’s the first time I felt like we were in control of the turnaround, not just reacting to it.”
Measurable outcomes and achievements from this implementation that demonstrate the transformative impact of intelliSPEC.
3 days saved in total turnaround duration, significantly accelerating project delivery.
100% reduction in manual data entry, eliminating errors and increasing operational efficiency.
Achieved 95% inspector adoption within the first week, demonstrating ease of use.
Zero missed assets during QA re-inspection, ensuring complete quality coverage.
Hailed as the "Best turnaround handover in 5 years" by the plant director.
Driving measurable operational improvements and setting new standards for efficiency and quality.